Recent projects

                                                                

Bund Garden Bridge

See More

Recent projects

                                                                

Glasgow Museum of Transport

See More

Recent projects

                                                                

Shahama Saadiyat Freeway, Abu-Dhabi:

See More

Recent projects

                                                                

Bund Garden Bridge

See More

Recent projects

                                                                

Dubai International Airport:

See More

Contact Us

Registered Office

Tel. +91 (0) 20 66472235
Fax. +91 (0) 20 66472232
Email: hr@kashecindia.net


Corporate Office

Tel: +91 (0) 20 66472235
Fax. +91 (0) 20 66472232
Email: hr@kashecindia.net

Construction of 30 m wide concrete road from Hadapsar to Saswad up to PMC limit

Location                      Pune                           Client Pune Municipal Corporation

Start Date                    November   2008       End Date        March 2011

Project Cost                Rs. 18 crores

Description                

The project involved the construction of 30 m wide six lane road. Quality control & supervision on entire execution of 1.3 km long concrete road, all CD works in the alignments, small bridges, box culverts including quality tests of materials & finished pavement, submitting of all reports (RFI, DPR, MPR) & contractors bill checking, co-ordination with contractor & client, all these procedures were carried out by Kashec Engineers Pvt. Ltd. 

Widening & Asphalting Mundhwa Road

Location:                    Pune, Maharashtra               Client: Pune Municipal Corporation

Start Date                    November   2006                   End Date        March 2011

Project Cost               Rs. 18 crores

Description    

The Project involved construction of 24 m Wide Four Lane Road. Quality Control & supervision on entire execution of 3.3 km long B.T. Road, all CD works in the alignments, small bridges, box culverts including quality tests of materials & finished pavements, submitting of all reports (RFI, DPR, MPR) & contractors bill checking, co-ordination with contractors & client.

Kashec was involved in ground surveys & investigation, geo-tech investigation for bridges & high embankments, final project report & final drawings, tender documents. Construction supervision like design review, contract management & quality control has been done by Kashec. 

Development of road from Bhairoba Pumping Station to Magarpatta City

Location                      Pune                                       Client Pune Municipal Corporation

Start Date                    November 2006                     End Date        August 2010

Project Cost                Rs. 14 crores

Description     ​      

The project involved construction of 18 m Wide Four Lane road. Pretender & post tender complete responsibility. Quality control & supervision on entire execution of 1.7 km long concrete road. All CD works in the alignments, box culverts including quality tests of materials & finished pavement, submitting of all reports (RFI, DPR, MPR) & contractors bill checking, co-ordination with contractor & client.